Understanding the cost overrun causation in construction megaprojects – a grounded systems thinking approach
View/ Open
Date
2021-12Author
Godawatte, Godawatte Arachchige Gimhan Rathnagee
Metadata
Show full item recordAbstract
Research background: The problem of cost overruns in construction megaprojects is a
‘complex problem’. Although a considerable amount of research has been conducted to
identify the isolated factors causing cost overruns in megaprojects, there is a lack of
holistic understanding of the complex causal interrelationships between the causes of cost
overruns. Therefore, to fulfil this research gap, adding a novel contribution to the existing
body of knowledge, adopting systems thinking approach, this thesis aims to holistically
examine and understand the cost overrun causation in construction megaprojects and
develop a model/substantive theory that represents the complex problem of cost overruns
in construction megaprojects.
Research methodology and design: The thesis adopted a qualitative research
methodology based on a case study research design. California High-Speed Rail project
was selected as the case study and data were collected from a range of sources. Data were
analysed using grounded theory method and systems thinking approach was used to
develop the model (systems map). Seven (07) theoretical propositions that emerged from
the data analysis were developed to explain the drivers of each systems map and their
cause and effect relationships. The developed model/substantive theory and the
underpinning propositions were validated using a two-round modified Delphi survey.
Important research findings: The holistic examination of the complex problem of cost
overruns revealed that the project cost overruns were an emergent ‘symptom’ caused by
multiple interrelated causes and events occurring at different levels and phases of the
project thus cannot be attributed to one single cause. Further to the current academic
explanations on cost overruns in the project management literature, findings of the
research revealed that that ignorance, impulsive decision-making, immature project
organisation, and political pressures collectively led to initiating the project with
unrealistic cost and schedule estimates and an undefined scope. Scope creep, inflation,
community pressure, lawsuits, and multiple delays were collectively responsible for cost
overruns during the execution phase.
Contribution to knowledge: Using systems thinking approach, this thesis holistically
examined the cause and effect relationships between the drivers of cost overruns in
megaprojects by developing a model/substantive theory (systems map) of cost overrun
causation. The developed systems map could be used as a tool for strategic decision-making in megaprojects to understand how cost overruns emerge as a result of multiple
interrelated causes and events occurring at different levels and phases of the project.